
Pickets yesterday outside Audubon School.Contractor blamed for fallen school roof
By Edith Herman
Public school officials yesterday blamed a private
roofing firm for the collapse of a roff at Audubon
School, 3500 N. Hoyne Av., on Sunday.
Dr. Frank Mattox, assistant superintendent for
operations services, said the school system will file an
insurance claim against Raney-Harris Inc., a roofing firm
which was in the process of resurfacing the roof.
The school was closed yesterday, but about 75 parents
picketed the building, demanding that the roof repairs be
completed before the school reopens.
Parents had been protesting the fact that the repairs
were going on while children were in classes and onw plan
to boycott the school until repairs are completed, said
Mrs. Barbara Gotski, PTA president.
Mattox said that three separate studies found the roof
was structurally sound. Mettings will be held with
parents today to review the investigations by the City
Building Department, Board of Education, and a private
architectural firm, Illinois Belli and Belli, he said.
The studies showed that the roof collapsed because it
was overloaded with building materials stored there by
workmen, said Manford Byrd, deputy superintendent of
schools.
The school is expected to reopen today after the
meeting with parents.
The firm was in the midst of resurfacing the
80-year-old roof as part of a Board of Education project.
Altho reports said the roof was structurally sound and
would not have collapsed under normal circumstances, the
principal of the building is not convinced.
"This building is not fit for any child,"
insists Miss Anabel McCutcheon, Audubon Principal.
"I'm dubious about putting teachers in it-plaster
can fall on tehir heads, too."
Miss McCutcheon insists that the roof should be
replaced instead of merely resurfaced. "One of our
parents warned the board the roof would collapse last
December. She was right."
Leaks in the roof were first found in 1971. The board
last July let contracts for the roof repairs and work did
not start until March, despite parent protests, Miss
McCutcheon said. "I guess we didn't throw enough
tantrums. No one listened."
"I'm frightened," Mrs. Gotski said.
"Our children could have been killed if the collapse
happened during the week."
The accident destroyed a third floor classroom, and
set off a sprinkler system which flooded the basement and
created extensive water damage. Paint and plaster also
are falling off the walls in the third floor corridor
because of the impact," Mrs. McCutcheon said.
Francis Cronin, director of plant operation, said the
roof was not resurfaced last fall because of
complications which delayed finalization of the building
contract, until Mid-September, too late to start roof
work.
However, he insists that the delay until March, when
work began, was not the cause of the accident.
"If the roof can't hold building materials, what
happens when a tornado hits," Miss McCutcheon asked.
- Tribune
|